By Rex ly
Mr. Lucas the ESUHSD Senior Manager of the Bond Program and overseer
- When did you originally expect the new building to be complete?
- We were anticipating for the new building to be complete in August.
Q.The buildings finished a little late, why do you think that is?
- Usually, there isn’t one reason or one event that creates a delay. Construction projects are complex and require a great deal of synchronized coordination. There are many factors such as equipment malfunctions, weather, and communication and overbooked are a few things that could cause a delay.
- When did you originally expect the new building to be complete?
- We were anticipating for the new building to be complete in August.
- Personally, did you think the building was a good idea?
- I think the building is a good idea. The project creates new spaces that Piedmont Hills can be proud of.
- Why is the building shaped the way it is?
- There is a strong slope from the sidewalk just outside of the D Building to the student lot (about 7 feet). It was shaped the way it is to work with and manage the slope.
With Construction worker Fuji Gerardo
- How do you feel working at school?
- It feels much safer working in a school.
- Do you still work regardless of the weather, such as if it rains?
- We work out here rain or shine.
- what is the hardest part of the construction?
- The hardest part was digging the foundation and over the winter break we had truckloads of dirt.
- Did you enjoy working on this building?
- Building is always more enjoyable when you know the people who will use it for many years to come
- Why do you think the new building was done late?
- It is hard to find substitutes when we need more manpower. There are only 10 to 12 of us working at a time
- How long do you work?
- 6:00 am to 2:00 pm.